What is the process?

The review process is as following:


  1. Application Submitted
  2. Application Deemed Complete by Staff
  3. Application Placed on Development Review Board Schedule and Applicant Notified
  4. Community “Heads Up”: Warning or Notice
  5. Staff Report Written, Mailed to Applicants, Posted Online
  6. Development Review Board Hearing Held
  7. Written Decision Issued
  8. If Approved, Applicant Satisfies all Applicable Conditions
  9. Applicant Applies for Zoning Permit and/or Submits Plat for Signature and Recording
  10. Zoning Permit Issued, Construction Begins
  11. Once Project is Complete a Certificate of Occupancy/Compliance Applied for and Issued if the Site Passes Inspection


Show All Answers

1. What is development review?
2. Which applications require development review?
3. Who does development review?
4. What are the regulations?
5. What is at the discretion of the Development Review Board?
6. What is the process?
7. Does Milton do a pre-application consultation?
8. How do I submit an application and what does it cost?
9. How long does it take?
10. Who can participate in a hearing?
11. Where can I see the details of a proposal?
12. Do I need to sign in?
13. How does the Development Review Board conduct the hearing?
14. How does the Development Review Board vote?
15. How are decisions issued?
16. What are the public notification requirements?